By ROEL R. LANDINGIN
Philippine Center for Investigative Journalism
(Conclusion)
Alonzo, who uses Berkoff’s paper in his
classes, says road projects fare somewhat better and tend to
yield higher economic returns than initially estimated because
of spillover effects. The EIRR on farm-to-market roads in the
small sample of projects examined by PCIJ were generally higher
after completion compared to appraisal.
But there are many exceptions, and one that
easily comes to mind is the majestic but costly San Juanico
Bridge that links Samar to former First Lady Imelda Marcos’s
native Leyte island.
"San Juanico was constructed several decades
too soon," says Alonzo who used to bring his students to the
bridge for the annual field trip years after it was built with
Japanese ODA loans in the early 1970s. "We’re in the bridge for
several hours already but we don’t see any cars or jeepneys,
only carabaos."
Public works engineers, he adds, used to joke
among themselves that average daily traffic (ADT) was not
measured in terms of vehicles but carabaos.
According to the project completion reports
reviewed by PCIJ, lower-than-expected returns of completed
projects stem from a variety of reasons, including extended
delays in completing the project, hefty cost increases, or weak
demand.
Various risks – economic, political and even
security – could hobble a project, dragging performance well
below expectations or even minimum standards. This is apparent
from even a cursory look at the three lenders’ biggest project
loans.
One of JBIC’s largest project loans in the
Philippines was a 32-billion-yen package signed in 1982 to
finance the construction of extra-high voltage transmission
lines that would bring power from the geothermal power plants in
Bicol and Leyte to Manila and Central Luzon.
Yet, after erecting more than 560 steel
towers and stringing up almost 250 kilometers of transmission
lines in May 1987, a year and a half behind schedule, the
borrower, National Power Corp. (Napocor), left the facilities
unused for over a decade.
Communist guerrilla attacks and pilferage,
which downed 11 towers, hampered the project. A more serious
problem was the unexpected cancellation or postponement of plans
to build several geothermal plants in Southern Luzon and the
Visayas.
"The original project design has become less
relevant in conjunction with overall power development plan,"
JBIC said in a project completion report prepared in October
2002. It did not bother to recalculate the project’s financial
return, which was likely to be very low or negative because of
the delay in using the project.
Similarly, the World Bank’s single biggest
project loan was a $203-million funding support in 1996 that
went mostly to building transmission lines connecting the
newly-built coal-fired power plants in Masinloc, Zambales, and
Sual, Pangasinan, to the rest of the Luzon power grid.
According to the Bank itself, the economic
rate of return for the project after completion in 2003 was
likely negative compared to original estimates of at least 20
percent because of low power rates, the slump in demand for
electricity in the wake of the Asian financial crisis, and
excessive power capacity because of overcontracting with the
independent power producers (IPPs).
The disappointing performance of the ODA-funded
power projects eventually exacted a heavy toll on Napocor. Since
2001, the state power company had been incurring massive
financial losses that hurt its ability to repay loans. In 2005,
the government had to bail out Napocor, assumed P500 billion of
the power firm’s foreign obligations, and sold off state-owned
power assets to repay debts.
Politics also ruined many a good ODA project,
such as the Second Subic Bay Freeport project, which was funded
by a $60-million World Bank loan that became effective toward
the end of the President Fidel Ramos’s term in late 1997. The
project aimed to improve power and water services in the special
economic zone and nearby Olongapo City.
In time, an extended political dispute,
triggered by then President Joseph Estrada’s decision to replace
Richard Gordon with Felicito Payumo as administrator of the
Subic Bay Metropolitan Authority (SBMA), delayed and reduced the
project’s scale.
Olongapo City, the Gordons’ political
bailiwick, backed out of plans to merge the city’s public
utilities department with that of the SBMA. A project to develop
a bulk water source in a nearby municipality for the free port
was delayed and eventually canceled.
Disappointing economic and financial returns
on completed foreign-assisted projects should temper claims that
ODA boosts economic growth and development in recipient
countries, regardless of specific circumstances.
JBIC, for example, says that its foreign
assistance in fiscal years 1996 to 2000 helped raise annual
economic output by 0.71 percent in the Philippines, 0.5 percent
in Indonesia and Thailand, and as much as 1.65 percent in
Vietnam. JBIC adds that ODA had a positive impact on per capita
gross domestic product "regardless of the differences of the
policy and institutional environment."
The Japanese embassy in Manila says that in
the Philippines, "13 percent of all national highways were
improved through Japan ODA." It notes that 200 new bridges,
including the Second Mandaue-Mactan Bridge and the San Juanico
Bridge, were funded by Japanese aid money.
But a close reading of the JBIC’s own
post-evaluation reports presents a more nuanced, if mixed,
picture. For example, economic returns on the Mandaue-Mactan
Bridge were lower after completion compared to appraisal because
of higher construction costs. And even those who have yet to
hear Alonzo’s carabao story remember the San Juanico Bridge
primarily as one of the costliest white elephants built during
the Marcos period.
The Japanese embassy also touts Terminal 2 of
the Ninoy Aquino International Airport, along with the
Cebu-Mactan International Airport, among the major airports
built with Japanese ODA. These airports "cater to about 1.3
million passengers taking domestic flights and about 8.3 million
taking international flights," says the embassy.
Yet JBIC’s post-evaluation report on NAIA 2
halved the estimated financial returns on the project to only
3.7 percent after completion. Said JBIC: "Owing to the increase
in the investment cost in peso terms and the decline of the
number of passengers to the Asian economic crisis, and to the
current limited use of Terminal 2."
To be sure, development aid could potentially
help poor and developing countries grow faster by adding to
savings and investments, especially in social development
projects that are not likely to get the interest of private
investors. Regions that enjoy high levels of infrastructure
investments, a big part of which is funded by ODA, grow much
faster and have less poverty incidence.
But the value of aid is diminished if capital
or investment projects such as roads, power plants or ports
financed by ODA generate returns that fall below expectations or
minimum benchmarks.
Still and all, the government has no way of
knowing, in a systematic and comprehensive way, which projects
are performing well and which are failing. NEDA keeps tabs on
ongoing projects and carefully measures time and cost overruns,
as well as disbursement and availment rates. The NEDA monitoring
stops after a project is finished.
There is as yet no system in place to check
how foreign-assisted projects are doing after completion
although NEDA’s project monitoring staff say they are trying to
build one.
In contrast, another agency, the Department
of Finance, which continues to strictly monitor the status of
ODA loans knows exactly when each amortization is due, and how
much more payments need to be made.
It’s time the government paid equal attention to both ODA
loans and the projects funded by those debts.