SEN. Rodolfo Biazon on Friday pressed for another inquiry on
the controversial Northrail project to find out why it costs 10 times more than
the proposed Southrail project considering that the two rail projects have
roughly the same specifications.
Biazon said Southrail would cost around $50 million to build
while Northrail is pegged at $503 million.
"The major issue is how come the Southrail component costs
only $50 million, longer by two kilometers than the Northrail, which is costing
us $503 million," Biazon said. His committee on housing held a hearing Friday to
check on the status of the Northrail project.
The Senate, constituting itself as the Committee of the
Whole, had conducted an earlier probe on the Northrail project but was not able
to finish it. Biazon said the new probe would also take a closer look at the
relocation of some 97,000 families displaced by the two rail projects.
The displaced families have taken up residence alongside the
railroad tracks as well as in the areas to be traversed by the rail projects.
Biazon said that so far, 46,000 of these families have been
relocated by government, some in Tanza, Cavite. He said more families would
actually be displaced and relocated because a bigger clearance is needed from
the projected tracks. He said relocating them to the provinces would take them
away from their jobs in Metro Manila.
The Northrail was conceptualized in 1994 during the term of
President Fidel Ramos but it was during the term of President Arroyo when the
project was firmed up with the signing of an executive agreement with the
Peoples' Republic of China. Under the agreement, China National Machinery and
Equipment Corp (CNMEG) was designated by the Chinese government to handle the
design, supply and construction of Phase 1 of the project, and the Export Import
Bank of China to take care of funding. Contracts and loan agreements have been
finalized and signed and the construction had begun last month.
The project is divided into four phases - Phase 1 from Caloocan to Clark
Field, Pampanga; Phase 2 from Clark Field to Subic Bay; Phase 3 from Caloocan to
Fort Bonifacio, Taguig City, and Phase 4 from Clark Field, Pampanga to San
Fernando, La Union. Expected project completion is 2011. - Dennis Gadil